20% Component of the IRA Utilization



                                                            CY 2012 ANNUAL INVESTMENT PLAN SUMMARY

       (BREAKDOWN OF PRIORITY PROJECTS TO BE FUNDED BY THE 20% DEVELOPMENT FUND)
         
         SCHED OF    
  STATUS OF IMPLEMENTATION   (AS OF OCTOBER 31, 2012
 IMPLEMENTATION   Funding    
Start Completion Expected Output Source 20% Dev't. TOTAL UNOBLIGATED AMOUNT PHYSICAL ACCOMPLISHMENT
Date Date     Fund  
Jan-12 Dec-12 50% completed Public Market 20%DF 500,000.00 500,000.00      145,534.36 10 units of concession spaces completed
             
Jan-12 Dec-12 Completed rehabilitation of Municipal  20%DF 100,000.00 100,000.00        51,420.00 regular maintenance, construction of walkways
    Cemetery        
Jan-12 Dec-12 Improved municipal/barangay road networks 20%DF 1,050,000.00 1,050,000.00      133,123.75 183mts concreted-montana, sn vicente, landican,tanday,dasitam (sn isidro, libertad, sn roque - not yet started)
             
 
Jan-12 Dec-12 Counterpart fund for LGSP/UNDP projects 20%DF 75,000.00 75,000.00        75,000.00 not yet started (farmers already reorganized)
    provided        
Jan-12 Dec-12 Sustained CRM Programs 20%DF 285,000.00 285,000.00        22,686.95 regular seaborne patrol (sequestered 2 pumpboats)
Jan-12 Dec-12 Sustained Waste Management Program 20%DF 2,200,000.00 2,200,000.00      807,825.52 12 units of vehicles acquired, 4 units bidded out
Jan-12 Dec-12 updated Municipal Land Use Plan 20%DF 400,000.00 400,000.00        65,400.00 70% parcelliary encoding of lots 
               
Jan-12 Dec-12 Improved water sources/services 20%DF 1,300,000.00 1,300,000.00      931,160.02 regualar operation/maintenance
Jan-12 Dec-12 Acquired parcel of Lot for housing project 20%DF 500,000.00 500,000.00      500,000.00 not started/acquired
               
Jan-12 Dec-12 Improved Cultural Center & facilities 20%DF 100,000.00 100,000.00      100,000.00 pow not completed
               
Jan-12 Dec-12 Improved Cultural Center & facilities 20%DF 80,000.00 80,000.00        65,510.50 not completed
               
Jan-12 Dec-12 Completed rehabilitation of Baliaut Spring 20%DF 100,000.00 100,000.00      100,000.00 not started
        TOTAL 6,690,000.00   2,997,661.10 50% ACCOMPLISHMENT


















DENIS MISAEL A. PAMAN






    Municipal Budget Officer




IRA UTILIZATION
As of August 31, 2012

FUNCTIONAL/PROGRAM/
PROJECT/ACTIVITY

APPROPRIATION
ALLOTMENT
OBLIGATION
UNOBLIGATED BALANCE
CAPITAL OUTLAY
(20%)Development Fund


Capital Outlay

IMPROVEMENT OF PUBLIC MARKET

IPROVEMENT OF MUNICIPAL CEMENTERY

ROAD IMPRV’T/CONCRETING/OPENING/MAINT

COUNTERPART FUND FOR SPECIAL PROJECTS(LGSP/UNDP)

COASTAL RESOURCE MNGT FUND(CRM)

WASTE MANAGEMENT

CLUP UPDATING

WATERWORKS IMPRV’T/MAINT/OPS

ESTABLISHMENT OF TRAINING CENTER

CONST’N/REPAIR OF CULTURAL FACILITIES

ACQUISITION OF LOT(EDUCATION/BP 220)

IMPRV’T OF BALIAUT SPRING(ADD’L FUND)

TOTAL






500,00.00



100,000.00

1,050,000.00

75,000.00


285,000.00


2,200,000.00

400,000.00

1,300,000.00

100,000.00


80,000.00


500,000.00


100,000.00


6,690,000.00






500,00.00



100,000.00

877,500.00

75,000.00


285,000.00


2,200,000.00

400,000.00

400,000.00

-


80,000.00


100,000.00


-


5,017,500.00






298,149.49



-

817,616.25

-


179,911.15


1,240,249.93

304,600.00

367,334.98

-


-


-


-


3,207,861.80










201,850.51



100,000.00

59,883.75

75,000.00


105,088.85


959,750.07

95,400.00

32,665.02

-


80,000.00


100,000.00


-


1,809,638.20







 C.Y 2012 ANNUAL INVESTMENT PLAN SUMMARY
Municipality of Baclayon

PROGRAM/PROJECT/ACTIVITY DESCRIPTION
IMPLEMENTING OFFICE
SCHED OF IMPLEMENTATION
EXPECTED OUTPUT
FUNDING DOURCE
20% DEV’T FUND
TOTAL
START DATE
COMPLETION DATE
Improvement of Public Market Block
LCE
Jan-12
Dec.-12
50% Completed Public Market
20% DF
500,000.00
500,000.00
Improvement of Municipal Cemetery
LCE
Jan-12
Dec-12
Completed Rehabilitation of Municipal Cemetery
20% DF
100,000.00
100,000.00
Road Improvement/ Concreting/Opening & Maintenance
MEO
Jan-12
Dec-12
Improved municipal/ barangay road networks
20% DF
1,050,000.00
1,050,000.00
Counterpart Fund for LGSP/ UNDP Projects
LCE
Jan-12
Dec-12
Counterpart for LGSP/UNDP projects provided
20% DF
75,000.00
75,000.00
Coastal Resource Management
LCE
Jan-12
Dec-12
Sustained CRM programs
20% DF
285,000.00
285,000.00
Waste Management Program
MPDO
Jan-12
Dec-12
Sustained Waste Management Program
20% DF
2,200,000.00
2,200,000.00
Comprehensive Land Use Plan Updating
MPDO
Jan-12
Dec-12
Updated Municipal Land Use Plan
20% DF
400,000.00
400,000.00
Waterworks System Development
LCE
Jan-12
Dec-12
Improved water sources/service
20% DF
1,300,000.00
1,300,000.00
Acquisition of Lot for Batas Pambansa 220
LCE
Jan-12
Dec-12
Acquired parcel of Lot for Housing Project
20& DF
500,000.00
500,000.00
Establishment of Manpower Training Center
LCE
Jan-12
Dec-12
Improved Cultural Center & facilities
20% DF
100,000.00
100,000.00
Repair/Construction of Cultural Center & Facilities
LCE
Jan-12
Dec-12
Improved Cultural Center & facilities
20% DF
50,000.00
50,000.00
Improvement Baliaut Spring
LCE
Jan-12
Dec-12
Completed rehabilitation of Baliaut Spring
10% DF
100,000.00
100,000.00
Prepared by:                                                                                                                                                                                                                                         
(SGD.) ARCHT. MARVIN FRANCIS U. APALE                        (SGD.) DENIS MISAEL A. PAMAN                                                             Municipal Planning & dev’t Coordinator                                                    Municipal Budget Officer                                                                                 
                                                        Approved by:               
                                              (SGD.) ATTY. A. ALVIN J. UY, ECE
                                                          Local Chief Executive